All ERCOT wind and solar plants · Curtailment map and ranking
Blevins Solar: curtailment and node price
A 272 MW solar plant in Falls County, Texas (North), in service 2026. It settles at resource node BLVN_RN in LZ_NORTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2025 | 283 | 25.9 | 9.2% | $30.95 | $32.94 | −$2.87 | 5% |
| 2026 to date | 459 | 40.0 | 8.7% | $31.00 | $33.93 | −$7.15 | 7% |
| Last 12 months | 586 | 56.9 | 9.7% | $31.09 | $33.64 | −$5.90 | 6% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Falls County
ERCOT's interconnection queue (October 2026 report) lists 7 projects in Falls County, 612 MW in all: 552 MW solar, 60 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Blevins Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Blevins Solar
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.