Camp Springs Wind 2: curtailment and node price
A 124 MW wind farm in Scurry County, Texas (West), in service 2007. It settles at resource node CSC_CSECG1_2 in LZ_WEST. Owner (public sources): Invenergy.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 231 | 77.7 | 33.7% | $28.65 | $35.71 | −$4.45 | 14% |
| 2025 | 282 | 79.2 | 28.0% | $29.82 | $42.18 | −$4.72 | 10% |
| 2026 to date | 203 | 70.2 | 34.6% | $27.81 | $32.33 | −$4.04 | 16% |
| Last 12 months | 280 | 87.9 | 31.3% | $28.56 | $35.34 | −$3.59 | 14% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Scurry County
ERCOT's interconnection queue (October 2026 report) lists 16 projects in Scurry County, 4,815 MW in all: 2,870 MW solar, 1,923 MW batteries, 22 MW wind. 1,414 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Camp Springs Wind 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Camp Springs Wind 2
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.