All ERCOT wind and solar plants · Curtailment map and ranking
Coral Solar: curtailment and node price
A 154 MW solar plant in Falls County, Texas (North), in service 2024. It settles at resource node CORALSLR_ALL in LZ_NORTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 235 | 11.2 | 4.7% | $24.94 | $26.41 | −$19.90 | 4% |
| 2025 | 327 | 24.4 | 7.5% | $31.03 | $32.66 | −$5.67 | 4% |
| 2026 to date | 221 | 27.2 | 12.3% | $31.53 | $33.93 | −$5.63 | 6% |
| Last 12 months | 297 | 31.0 | 10.5% | $31.55 | $33.64 | −$5.31 | 5% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Falls County
ERCOT's interconnection queue (October 2026 report) lists 7 projects in Falls County, 612 MW in all: 552 MW solar, 60 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Coral Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Coral Solar
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.