Delilah Solar 2: curtailment and node price

A 318 MW solar plant in Red River County, Texas (North), in service 2026. It settles at resource node TTRSW_RN in LZ_NORTH.

0%of its potential output curtailed in the last 12 months (0.4 GWh). #349 of 494 ERCOT wind and solar plants by curtailed energy.
$33.91average real-time price at its node, per MWh, against $33.64 in its load zone, a $0.27 premium
$20.51average node price while it was curtailed, weighted by the curtailed energy
3%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
20255970.90.1%$31.64$32.66$20.964%
2026 to date5300.10.0%$34.27$33.93$17.103%
Last 12 months7050.40.1%$33.91$33.64$20.513%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

What's coming in Red River County

ERCOT's interconnection queue (October 2026 report) lists 4 projects in Red River County, 331 MW in all: 201 MW solar, 130 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.

The full picture

A LoadSettle asset report on Delilah Solar 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.

Request a report on Delilah Solar 2

The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.