All ERCOT wind and solar plants · Curtailment map and ranking

Fluvanna Renewable 1 B: curtailment and node price

A 76 MW wind farm in Scurry County, Texas (West), in service 2017. It settles at resource node FLUVANNA_1_2 in LZ_WEST.

3%of its potential output curtailed in the last 12 months (9.3 GWh). #199 of 494 ERCOT wind and solar plants by curtailed energy.
$25.27average real-time price at its node, per MWh, against $35.34 in its load zone, a $10.07 discount
−$40.78average node price while it was curtailed, weighted by the curtailed energy
18%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
2024 (from Jan 24)2462.00.8%$23.18$35.71−$40.0113%
202528624.28.5%$24.46$42.18−$39.7217%
2026 to date2035.12.5%$25.23$32.33−$36.6520%
Last 12 months2879.33.3%$25.27$35.34−$40.7818%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

What's coming in Scurry County

ERCOT's interconnection queue (October 2026 report) lists 16 projects in Scurry County, 4,815 MW in all: 2,870 MW solar, 1,923 MW batteries, 22 MW wind. 1,414 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.

The full picture

A LoadSettle asset report on Fluvanna Renewable 1 B adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.