Grizzly Ridge Solar: curtailment and node price

A 62 MW solar plant in Hamilton County, Texas (North), in service 2023. It settles at resource node POTSVIL_RN in LZ_NORTH.

20%of its potential output curtailed in the last 12 months (6.0 GWh). #226 of 494 ERCOT wind and solar plants by curtailed energy.
$38.10average real-time price at its node, per MWh, against $33.64 in its load zone, a $4.46 premium
$3.83average node price while it was curtailed, weighted by the curtailed energy
4%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
2024 (from Jan 24)17825.114.1%$26.54$26.41−$0.445%
202516336.722.4%$33.99$32.66$1.454%
2026 to date6.10.12.2%$37.18$33.93$43.784%
Last 12 months29.96.020.0%$38.10$33.64$3.834%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

The full picture

A LoadSettle asset report on Grizzly Ridge Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.

Request a report on Grizzly Ridge Solar

The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.