Hart Wind 2: curtailment and node price
A 164 MW wind farm in Castro County, Texas (Panhandle), in service 2025. It settles at resource node HART_WND_RN in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2025 | 350 | 2.0 | 0.6% | $24.78 | $41.75 | −$61.64 | 16% |
| 2026 to date | 592 | 0.2 | 0.0% | $24.62 | $32.33 | −$42.74 | 22% |
| Last 12 months | 820 | 2.1 | 0.3% | $23.68 | $35.34 | −$61.89 | 24% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Castro County
ERCOT's interconnection queue (October 2026 report) lists 7 projects in Castro County, 2,304 MW in all: 1,110 MW solar, 553 MW batteries, 641 MW wind. 729 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Hart Wind 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.