All ERCOT wind and solar plants · Curtailment map and ranking
Hhgt: curtailment and node price
A wind farm in Texas (Texas). It settles at resource node HHGT_KENDAL in LZ_SOUTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 401 | 1.0 | 0.3% | $27.81 | $30.43 | −$45.80 | 4% |
| 2025 | 438 | 3.0 | 0.7% | $33.96 | $33.50 | −$21.50 | 4% |
| 2026 to date | 350 | 4.6 | 1.3% | $32.57 | $31.93 | $15.05 | 3% |
| Last 12 months | 483 | 5.0 | 1.0% | $34.17 | $33.12 | $11.45 | 3% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on Hhgt adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.