All ERCOT wind and solar plants · Curtailment map and ranking

Hhollow4: curtailment and node price

A wind farm in Texas (Texas). It settles at resource node HHOLLW4_WND1 in LZ_WEST.

No full 12 months of data yet.

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
2024 (from Jan 24)2580.10.0%$24.26$35.71$20.2913%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

The full picture

A LoadSettle asset report on Hhollow4 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.

Request a report on Hhollow4

The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.