Hickman (Santa Rita Wind) 2: curtailment and node price

A 295 MW wind farm in Reagan County, Texas (West), in service 2018. It settles at resource node HICK_G1_G2 in LZ_WEST.

1%of its potential output curtailed in the last 12 months (4.0 GWh). #248 of 494 ERCOT wind and solar plants by curtailed energy.
$31.28average real-time price at its node, per MWh, against $35.34 in its load zone, a $4.06 discount
−$32.29average node price while it was curtailed, weighted by the curtailed energy
13%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
2024 (from Jan 24)5694.00.7%$29.45$35.71−$24.5512%
20256092.70.4%$34.03$42.18−$24.129%
2026 to date4281.90.4%$29.11$32.33−$34.0915%
Last 12 months5954.00.7%$31.28$35.34−$32.2913%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

What's coming in Reagan County

ERCOT's interconnection queue (October 2026 report) lists 3 projects in Reagan County, 618 MW in all: 308 MW batteries, 310 MW wind. 310 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.

The full picture

A LoadSettle asset report on Hickman (Santa Rita Wind) 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.

Request a report on Hickman (Santa Rita Wind) 2

The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.