Jumbo Road Wind 2: curtailment and node price
A 154 MW wind farm in Deaf Smith County, Texas (Panhandle), in service 2015. It settles at resource node HRFDWIND_ALL in LZ_WEST. Owner (public sources): BHE Renewables (Berkshire Hathaway Energy).
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 462 | 4.5 | 1.0% | $19.05 | $35.71 | −$35.87 | 24% |
| 2025 | 465 | 120 | 25.7% | $23.36 | $42.18 | −$6.54 | 23% |
| 2026 to date | 357 | 128 | 36.0% | $24.86 | $32.33 | −$4.96 | 21% |
| Last 12 months | 497 | 200 | 40.4% | $23.98 | $35.34 | −$5.46 | 23% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Deaf Smith County
ERCOT's interconnection queue (October 2026 report) lists 11 projects in Deaf Smith County, 6,392 MW in all: 3,169 MW solar, 207 MW batteries, 1,740 MW wind, 1,275 MW gas. 3,119 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Jumbo Road Wind 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.