All ERCOT wind and solar plants · Curtailment map and ranking
Kellam Solar: curtailment and node price
A 60 MW solar plant in Van Zandt County, Texas (North), in service 2020. It settles at resource node KELAMSL_U1 in LZ_NORTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 112 | 5.9 | 5.3% | $26.05 | $26.41 | $0.23 | 2% |
| 2025 | 115 | 4.6 | 4.0% | $33.08 | $32.66 | −$2.74 | 3% |
| 2026 to date | 88.4 | 6.3 | 7.1% | $32.84 | $33.93 | −$3.65 | 3% |
| Last 12 months | 117 | 7.7 | 6.6% | $32.59 | $33.64 | −$3.48 | 3% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Van Zandt County
ERCOT's interconnection queue (October 2026 report) lists 8 projects in Van Zandt County, 986 MW in all: 272 MW solar, 714 MW batteries. 682 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Kellam Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Kellam Solar
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.