Lone Star Wind 2 (Post Oak): curtailment and node price
A 198 MW wind farm in Shackelford County, Texas (West), in service 2007. It settles at resource node LNCRK_ALL in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 444 | 42.8 | 9.6% | $23.82 | $35.71 | −$10.91 | 12% |
| 2025 | 459 | 37.1 | 8.1% | $29.64 | $42.18 | −$11.34 | 10% |
| 2026 to date | 316 | 61.1 | 19.3% | $27.30 | $32.33 | −$8.93 | 16% |
| Last 12 months | 451 | 71.1 | 15.8% | $28.28 | $35.34 | −$9.29 | 14% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Shackelford County
ERCOT's interconnection queue (October 2026 report) lists 2 projects in Shackelford County, 410 MW in all: 204 MW solar, 206 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Lone Star Wind 2 (Post Oak) adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Lone Star Wind 2 (Post Oak)
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.