Mariah Del Norte 2: curtailment and node price
A 115 MW wind farm in Parmer County, Texas (Panhandle), in service 2017. It settles at resource node MARIAH_ALL in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 424 | 7.2 | 1.7% | $19.05 | $35.71 | −$33.94 | 24% |
| 2025 | 416 | 1.0 | 0.2% | $23.36 | $42.18 | −$40.83 | 23% |
| 2026 to date | 325 | 0.3 | 0.1% | $24.86 | $32.33 | −$37.37 | 21% |
| Last 12 months | 448 | 1.2 | 0.3% | $23.98 | $35.34 | −$40.63 | 23% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on Mariah Del Norte 2 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Mariah Del Norte 2
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.