Oci Alamo 4 Solar-Bracketville: curtailment and node price
A 38 MW solar plant in Kinney County, Texas (South), in service 2014. It settles at resource node ECLIPSE_UN1 in LZ_SOUTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 75.0 | 2.3 | 3.1% | $34.58 | $30.43 | −$5.58 | 4% |
| 2025 | 74.9 | 4.3 | 5.7% | $41.56 | $33.50 | −$4.27 | 5% |
| 2026 to date | 54.2 | 3.0 | 5.6% | $34.88 | $31.93 | −$5.34 | 7% |
| Last 12 months | 72.6 | 4.1 | 5.6% | $36.92 | $33.12 | −$4.73 | 6% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Kinney County
ERCOT's interconnection queue (October 2026 report) lists 9 projects in Kinney County, 945 MW in all: 743 MW solar, 202 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Oci Alamo 4 Solar-Bracketville adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.