Old Settler Wind: curtailment and node price
A 151 MW wind farm in Floyd County, Texas (Panhandle), in service 2017. It settles at resource node COTPLNS_RN in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 520 | 17.0 | 3.3% | $19.36 | $35.71 | −$31.07 | 24% |
| 2025 | 548 | 8.1 | 1.5% | $23.35 | $42.18 | −$30.89 | 23% |
| 2026 to date | 430 | 2.2 | 0.5% | $24.89 | $32.33 | −$31.18 | 21% |
| Last 12 months | 593 | 3.8 | 0.6% | $24.09 | $35.34 | −$30.81 | 23% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on Old Settler Wind adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.