All ERCOT wind and solar plants · Curtailment map and ranking
Phoenix Solar: curtailment and node price
A 84 MW solar plant in Fannin County, Texas (North), in service 2021. It settles at resource node PHOENIX_RN in LZ_NORTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 171 | 9.3 | 5.4% | $26.16 | $26.41 | −$0.11 | 3% |
| 2025 | 178 | 17.2 | 9.7% | $31.89 | $32.66 | −$2.04 | 3% |
| 2026 to date | 126 | 13.1 | 10.4% | $33.97 | $33.93 | −$3.59 | 3% |
| Last 12 months | 166 | 16.9 | 10.2% | $33.42 | $33.64 | −$3.06 | 3% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Fannin County
ERCOT's interconnection queue (October 2026 report) lists 3 projects in Fannin County, 1,363 MW in all: 192 MW batteries, 180 MW wind, 991 MW gas. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Phoenix Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Phoenix Solar
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.