A 327 MW solar plant in Brown County, Texas (North), in service 2023. It settles at resource node RADN_SLR_ALL in LZ_NORTH.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 657 | 37.2 | 5.7% | $24.75 | $26.41 | −$10.56 | 12% |
| 2025 | 714 | 49.3 | 6.9% | $30.04 | $32.66 | −$4.63 | 8% |
| 2026 to date | 517 | 24.8 | 4.8% | $26.87 | $33.93 | −$21.99 | 16% |
| Last 12 months | 688 | 28.9 | 4.2% | $28.51 | $33.64 | −$19.48 | 13% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Brown County
ERCOT's interconnection queue (October 2026 report) lists 9 projects in Brown County, 2,104 MW in all: 858 MW solar, 1,246 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Radian Solar adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Radian Solar
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.