Sage Draw Wind: curtailment and node price
A 338 MW wind farm in Lynn County, Texas (West), in service 2022. It settles at resource node TAHOKA_ALL in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 1105 | 2.5 | 0.2% | $27.67 | $35.71 | −$31.07 | 13% |
| 2025 | 1164 | 21.0 | 1.8% | $28.74 | $42.18 | −$47.39 | 16% |
| 2026 to date | 882 | 0.1 | 0.0% | $30.32 | $32.33 | −$32.51 | 16% |
| Last 12 months | 1225 | 11.4 | 0.9% | $30.54 | $35.34 | −$58.17 | 16% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on Sage Draw Wind adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Sage Draw Wind
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.