South Plains Wind 1: curtailment and node price
A 200 MW wind farm in Floyd County, Texas (Panhandle), in service 2015. It settles at resource node SPLAIN1_RN in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 706 | 160 | 22.6% | $19.36 | $35.71 | −$13.38 | 24% |
| 2025 | 708 | 35.1 | 5.0% | $23.35 | $42.18 | −$24.39 | 23% |
| 2026 to date | 570 | 8.5 | 1.5% | $24.89 | $32.33 | −$23.01 | 21% |
| Last 12 months | 773 | 19.4 | 2.5% | $24.09 | $35.34 | −$23.44 | 23% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on South Plains Wind 1 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on South Plains Wind 1
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.