All ERCOT wind and solar plants · Curtailment map and ranking

Strategic Solar 1: curtailment and node price

A 135 MW solar plant in Ellis County, Texas (North), in service 2022. It settles at resource node STRATEGC_RN in LZ_NORTH.

9%of its potential output curtailed in the last 12 months (23.7 GWh). #121 of 494 ERCOT wind and solar plants by curtailed energy.
$32.51average real-time price at its node, per MWh, against $33.64 in its load zone, a $1.13 discount
−$3.93average node price while it was curtailed, weighted by the curtailed energy
3%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
2024 (from Jan 24)29312.84.4%$25.97$26.41−$0.142%
202527722.38.0%$32.74$32.66−$1.762%
2026 to date21119.19.0%$32.30$33.93−$4.373%
Last 12 months27723.78.6%$32.51$33.64−$3.933%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

What's coming in Ellis County

ERCOT's interconnection queue (October 2026 report) lists 26 projects in Ellis County, 5,761 MW in all: 1,661 MW solar, 3,152 MW batteries, 898 MW gas, 50 MW other. 681 MW of it has signed interconnection agreements, the part most likely to be built. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.

The full picture

A LoadSettle asset report on Strategic Solar 1 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.