All ERCOT wind and solar plants · Curtailment map and ranking

Swft: curtailment and node price

A solar plant in Texas (Texas). It settles at resource node SWFT_SLR_RN in LZ_WEST.

6%of its potential output curtailed in the last 12 months (21.1 GWh). #131 of 494 ERCOT wind and solar plants by curtailed energy.
$37.71average real-time price at its node, per MWh, against $35.34 in its load zone, a $2.37 premium
−$6.17average node price while it was curtailed, weighted by the curtailed energy
10%of hours with the node priced at or below $0

By year

PeriodPotential GWhCurtailed GWhCurtailedNode $/MWhLoad zone $/MWhNode while curtailedHours ≤ $0
20253307.82.4%$45.19$42.18$1.265%
2026 to date27221.17.8%$33.42$32.33−$6.1713%
Last 12 months36321.15.8%$37.71$35.34−$6.1710%

Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.

The full picture

A LoadSettle asset report on Swft adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.