All ERCOT wind and solar plants · Curtailment map and ranking
Trinity Hills Wind 1: curtailment and node price
A 103 MW wind farm in Archer County, Texas (West), in service 2012. It settles at resource node TRINITY_ALL in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 355 | 1.6 | 0.4% | $22.91 | $35.71 | −$53.33 | 12% |
| 2025 | 384 | 0.2 | 0.1% | $28.66 | $42.18 | −$15.44 | 10% |
| 2026 to date | 293 | 0.0 | 0.0% | $27.07 | $32.33 | $3.43 | 15% |
| Last 12 months | 409 | 0.1 | 0.0% | $27.65 | $35.34 | −$23.92 | 14% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
What's coming in Archer County
ERCOT's interconnection queue (October 2026 report) lists 6 projects in Archer County, 808 MW in all: 309 MW solar, 500 MW batteries. None of it has a signed interconnection agreement yet. New plants near the same substations can raise curtailment and widen the discount at the node. The whole queue.
The full picture
A LoadSettle asset report on Trinity Hills Wind 1 adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Trinity Hills Wind 1
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.