All ERCOT wind and solar plants · Curtailment map and ranking
Whirlwind Energy: curtailment and node price
A 60 MW wind farm in Floyd County, Texas (Panhandle), in service 2007. It settles at resource node WEC_WECG1 in LZ_WEST.
By year
| Period | Potential GWh | Curtailed GWh | Curtailed | Node $/MWh | Load zone $/MWh | Node while curtailed | Hours ≤ $0 |
|---|---|---|---|---|---|---|---|
| 2024 (from Jan 24) | 105 | 12.2 | 11.6% | $24.73 | $35.71 | −$3.36 | 11% |
| 2025 | 105 | 15.9 | 15.1% | $34.10 | $42.18 | −$3.77 | 8% |
| 2026 to date | 75.4 | 17.0 | 22.6% | $29.31 | $32.33 | −$5.42 | 14% |
| Last 12 months | 106 | 22.1 | 20.8% | $29.83 | $35.34 | −$5.24 | 13% |
Curtailed = available capacity above ERCOT's dispatch target in every 5-minute run, so it includes economic backdown as well as congestion. Potential = available capacity. Prices are ERCOT real-time settlement point prices. Data 2024-01-24 to 2026-09-17; ERCOT publishes dispatch data 60 days after the fact. Last 12 months = 2025-09-18 to 2026-09-17.
The full picture
A LoadSettle asset report on Whirlwind Energy adds what the curtailment and prices mean for revenue: capture price and basis to the hubs, a revenue bridge, day-ahead vs real-time, which transmission limits move this node and by how much, and what ERCOT's congestion auctions price for the next two years. See a sample report.
Request a report on Whirlwind Energy
The first five reports are free for lenders, buyers and developers, in exchange for 15 minutes of feedback.